Export Power Management and Load Monitoring By CT

0
162

1. Background

Load Monitoring allows users to see whatโ€™s happening on their system in real time through the SolisCloud platform โ€” including:

  • Load-side power and energy
  • Grid voltage, current, power, and energy
  • 24-hour load monitoring (data is uploaded even at night)

This makes it much easier to understand household consumption and overall system behaviour.

This guide explains how to set up Load Monitoring using a CT clamp.

2. Applicable Inverters

Below are the inverter series which support the CT solution for the export power management and 24H load monitoring.

SolutionModelSpecificationInverter SeriesFunction 1Function2Software Version support function2
CT SolutionCTSA016-100ACT:100A/33.33mAS6-GR1P(0.7-3.6)K-MโˆšโˆšV8903
S6-GR1P(2.5-6)KโˆšโˆšV8903
S5-GR1P(7-10)KโˆšโˆšV8903
Solis-mini-(0.7-3.6)K-4Gโˆš  
Solis-1P(2.5-6)K-4Gโˆš  
Solis-1P(7-8)K-5Gโˆš  
S6-GR1P(7-8)K2โˆšโˆšV8903
S6-GR1P(2.5-6)K-SโˆšโˆšV4008

Function 1: Export Power Management

Function 2: 24-hour Load Monitoring

> Note: Function 1 (export control) automatically includes Function 2.

Important:

The CT solution is only suitable for systems with one inverter. For multi-inverter systems, use the EPM solution instead.

Also Read  Indiaโ€™s Solar Manufacturing Capacity to Surge as Pahal Solar Breaks Ground on 4 GW Integrated Facility in Surat

3. How To Use

1. Check Your Inverter

The CT method works only on Solis single-phase inverters with a built-in CT port.

Some versions have a Meter Port instead โ€” confirm with your Solis sales representative before ordering.

2.  CT Installation

The CT clamp is used to detect power flow at the grid connection point. If export power reaches the limit you set, the inverter will automatically reduce output.

Installation rules:

Clamp must be installed on the live (hot) wire at the grid connection point. The arrow on the CT must face towards the grid.Follow the wiring guidance shown in Solis documentation.

Cable connection of CT solution

3. Operation step

Below are the two setup methods depending on the function you want.

Function 1: 24-Hour Consumption Load Monitoring Only (Smart Sensor)

After installing the CT, follow the steps below to enable the 24-hour load monitoring function:

Step 1: Open โ€œInternal EPM Setโ€ on the inverter LCD screen

Advanced Settings โ†’ Password: 0010 โ†’ Internal EPM Set

Step 2: Select โ€œLoadMonitor_CTโ€ (Option 5)

Also Read  RWE Completes 100 MW Lafitte Solar Project In Louisiana, Powered By Long-Term PPA With Meta, Set To Serve 17,000 Homes

Advanced Settings โ†’ Password: 0010 โ†’ Internal EPM Set โ†’ Mode Select โ†’ LoadMonitor_CT

Step 3: Enable the 24H Switch

Advanced Settings โ†’ Password: 0010 โ†’ 24H Switch โ†’ Enable

Step 4: Configure the Solis monitoring system

(Refer to the monitoring device manual)

Function 2: Export Power Management + 24-Hour Consumption Load Monitoring (Smart Sensor)

After installing the CT, follow the steps below to enable export power management together with 24-hour load monitoring:

Step 1: Open โ€œInternal EPM Setโ€ on the inverter LCD screen

Advanced Settings โ†’ Password: 0010 โ†’ Internal EPM Set

Step 2: Select โ€œCurrent Sensorโ€ (Option 6)

Advanced Settings โ†’ Password: 0010 โ†’ Internal EPM Set โ†’ Mode Select โ†’ Current Sensor

Step 3: Set the โ€œCT Sampling Ratioโ€ to 3000:1

Advanced Settings โ†’ Password: 0010 โ†’ Internal EPM Set โ†’ Mode Select โ†’ Current Sensor โ†’ CT Sampling Ratio โ†’ 3000:1

Step 4: Enable the 24H Switch

Advanced Settings โ†’ Password: 0010 โ†’ 24H Switch โ†’ Enable

Step 5: Set the Backflow Power Limit

Choose how much power your system is allowed to export to the grid.

Also Read  Fox ESS SEA Launches First 125kW Three-Phase Energy Storage Project in Vietnam with VINASOL

Advanced Settings โ†’ Password: 0010 โ†’ Internal EPM Set โ†’ Backflow power

Step 6: Ensure โ€œFailsafe ON/OFFโ€ is set to ON

(Default is ON)

Advanced Settings โ†’ Password: 0010 โ†’ Internal EPM Set โ†’ Failsafe ON/OFF

Step 7: Configure the Solis monitoring system

(Refer to the monitoring device manual)

4.Conclude

Solis inverters with CT support can:

  • Monitor load consumption 24 hours a day, even at night
  • Control export power dynamically, adjusting inverter output to prevent unwanted export
  • Improve system stability and comply with local export-limit rules

For example, if your household load drops, the inverter will automatically reduce output so the system does not send power back to the grid.