Malaysia’s Corporate Renewable Energy Supply Scheme (CRESS) is expected to become more attractive for renewable energy developers and corporate electricity buyers following changes to its grid access charges. However, project execution, land availability and transmission connectivity remain major challenges, with developers facing a strict commissioning deadline of 31 December 2028. According to Wood Mackenzie, the revised framework improves project economics and provides greater cost certainty, but the ability to complete projects on time will determine who benefits from the changes.
On 18 September 2026, Malaysia’s Ministry of Energy Transition and Water Transformation (PETRA) announced the CRESS Acceleration Package, reducing the System Access Charge (SAC) payable by developers from MYR200/MWh (US$49/MWh) to MYR140/MWh (US$34/MWh). The reduction was introduced to improve the financial attractiveness of renewable energy projects and encourage greater corporate renewable electricity procurement.
However, the Energy Commission subsequently clarified that green electricity consumers would also need to pay an additional MYR40/MWh (US$10/MWh) charge. This charge may be revised during future Regulatory Period tariff reviews, bringing the effective grid access charge to MYR180/MWh (US$44/MWh).
The revised structure provides developers and project lenders with greater financial predictability. The MYR140/MWh developer charge will remain fixed for the first ten years of project operations, helping sponsors estimate revenues and assess project returns. Meanwhile, the additional MYR40/MWh consumer charge will remain subject to future tariff adjustments, shifting part of the regulatory cost risk to electricity buyers.
Wood Mackenzie research analyst Alvin Tan said the most important feature of the revised framework is the redistribution of risk between developers and off-takers. While developers benefit from ten years of cost certainty, corporate electricity buyers will need to account for potential increases in grid access charges during their agreements.
The impact could extend beyond the initial ten-year period. Corporate Power Purchase Agreements (CPPAs) generally run for 15 to 21 years, meaning several contracts will continue after the fixed-rate period ends. PETRA has not yet clarified how the SAC will be calculated beyond the first ten years. Developers and lenders are therefore expected to include different cost assumptions for the remaining contract period when evaluating project returns.
Despite these uncertainties, CRESS electricity procurement costs are expected to remain competitive against conventional utility tariffs. Wood Mackenzie estimates that the total delivered cost of CRESS electricity will be approximately US$95/MWh in 2026, making it competitive with High Voltage (HV) and Ultra High Voltage (UHV) electricity tariffs. The overall procurement cost is projected to increase by only around 8% through 2038, with renewable generation costs remaining the primary factor influencing competitiveness.
Project readiness, however, remains a major concern. Around 3,148 MW of capacity has been registered under CRESS across 11 developers and eight corporate buyers. However, the actual development progress and readiness of these projects remain uncertain.
With the commissioning deadline fixed at 31 December 2028 and no extensions expected, developers have limited time to complete project development. Utility-scale solar projects generally require 18 to 24 months from construction to commissioning. This leaves a narrow period to secure land, obtain permits, arrange financing and finalise grid connection arrangements.
Developers also face competition under Malaysia’s Large Scale Solar (LSS) programme for suitable land and available transmission capacity. Unlike conventional utility procurement, CRESS developers must identify grid injection points and bear the associated network reinforcement costs.
Tan highlighted that reducing the SAC improves project economics but does not increase land availability or transmission capacity. Developers with secured project sites, financing arrangements and clear grid connection plans are expected to have an advantage.
For corporate electricity buyers, the revised framework also creates pressure to move quickly. Delayed procurement could limit access to more advanced projects and reduce their negotiating position. Ultimately, the success of Malaysia’s CRESS Acceleration Package will depend not only on improved pricing but also on the ability of developers and off-takers to convert registered capacity into operational renewable energy projects before the 2028 deadline.