GERC Rejects Exemption Plea, Directs INR 40 Crore Bank Guarantee For 200 MW Hybrid Project In Gujarat

The Gujarat Electricity Regulatory Commission (GERC) has rejected a petition filed by renewable energy developer Parighosh Realtors and Developers LLP seeking exemption from submitting a ₹40 crore Bank Guarantee for its proposed 200 MW wind-solar hybrid project in Gujarat. In an order dated November 16, 2026, the commission directed the company to comply with the financial security requirements prescribed under Gujarat’s Renewable Energy Connectivity Procedure, 2025.

Oriana

The project is planned in Absada Taluka of Kutch district, Gujarat. Parighosh Realtors had applied for grid connectivity at the 220 kV Bhachunda substation in December 2024. Gujarat Energy Transmission Corporation Limited (GETCO) granted provisional connectivity in November 2025. However, in May 2026, GETCO asked the developer to submit an Associated Transmission System (ATS) Bank Guarantee of ₹20 lakh per MW, bringing the total requirement to ₹40 crore.

ReNew

Challenging the requirement, Parighosh Realtors argued that the Bhachunda substation had already been commissioned and operational since December 2020 under the centrally funded Green Energy Corridor scheme. The developer maintained that no new dedicated transmission infrastructure was being developed specifically for its project. Therefore, it argued that GETCO would not face any risk of stranded transmission assets.

The company also highlighted that it had already paid the applicable application fee and submitted a separate Security Bank Guarantee of ₹20 crore. According to the developer, demanding an additional ₹40 crore guarantee was unnecessary and disproportionate to the actual infrastructure requirements of the project.

GETCO opposed the petition, stating that the operational status of the substation did not mean sufficient transmission capacity was available to accommodate another 200 MW of renewable power. The utility explained that more than 1,460 MW of renewable and conventional generation capacity was already connected to the Bhachunda-Varsana-Nakhatrana transmission corridor.

Also Read  Ministry Of Power Releases NEDSF 2026 To Standardize Electricity Data Sharing Across India

GETCO further explained that accommodating the proposed project would require significant strengthening of the transmission network, including new 400 kV transmission lines. The Bhachunda-Varsana line has been delayed until December 2027 due to Supreme Court restrictions related to the protection of the Great Indian Bustard.

After examining the submissions, GERC concluded that the availability of an operational substation does not automatically establish sufficient capacity across the wider transmission network. Since the project required future transmission system strengthening, its connectivity application was covered under Clause 7.3 of the Connectivity Procedure, 2025.

The commission reiterated that developers must follow approved regulatory procedures and individual exemptions cannot be granted against mandatory requirements. Accordingly, GERC dismissed the petition and directed Parighosh Realtors to furnish the ₹40 crore Bank Guarantee for securing final grid connectivity for its proposed 200 MW wind-solar hybrid project.


Discover more from SolarQuarter

Subscribe to get the latest posts sent to your email.

LEAVE A REPLY

This site uses Akismet to reduce spam. Learn how your comment data is processed.

RELATED ARTICLES

Subscribe Today

GET EXCLUSIVE FULL ACCESS TO PREMIUM CONTENT

SUPPORT CLEANTECH JOURNALISM

EXPERT ANALYSIS OF AND EMERGING TRENDS

TOPICAL VIDEO WEBINARS

Get unlimited access to our EXCLUSIVE Content and our archive of subscriber stories.

Exclusive content this week

Latest article

More articles

- Advertisement -Newspaper WordPress Theme