The Gujarat Electricity Regulatory Commission (GERC) has rejected a petition filed by renewable energy developer Parighosh Realtors and Developers LLP seeking exemption from submitting a ₹40 crore Bank Guarantee for its proposed 200 MW wind-solar hybrid project in Gujarat. In an order dated November 16, 2026, the commission directed the company to comply with the financial security requirements prescribed under Gujarat’s Renewable Energy Connectivity Procedure, 2025.
The project is planned in Absada Taluka of Kutch district, Gujarat. Parighosh Realtors had applied for grid connectivity at the 220 kV Bhachunda substation in December 2024. Gujarat Energy Transmission Corporation Limited (GETCO) granted provisional connectivity in November 2025. However, in May 2026, GETCO asked the developer to submit an Associated Transmission System (ATS) Bank Guarantee of ₹20 lakh per MW, bringing the total requirement to ₹40 crore.
Challenging the requirement, Parighosh Realtors argued that the Bhachunda substation had already been commissioned and operational since December 2020 under the centrally funded Green Energy Corridor scheme. The developer maintained that no new dedicated transmission infrastructure was being developed specifically for its project. Therefore, it argued that GETCO would not face any risk of stranded transmission assets.
The company also highlighted that it had already paid the applicable application fee and submitted a separate Security Bank Guarantee of ₹20 crore. According to the developer, demanding an additional ₹40 crore guarantee was unnecessary and disproportionate to the actual infrastructure requirements of the project.
GETCO opposed the petition, stating that the operational status of the substation did not mean sufficient transmission capacity was available to accommodate another 200 MW of renewable power. The utility explained that more than 1,460 MW of renewable and conventional generation capacity was already connected to the Bhachunda-Varsana-Nakhatrana transmission corridor.
GETCO further explained that accommodating the proposed project would require significant strengthening of the transmission network, including new 400 kV transmission lines. The Bhachunda-Varsana line has been delayed until December 2027 due to Supreme Court restrictions related to the protection of the Great Indian Bustard.
After examining the submissions, GERC concluded that the availability of an operational substation does not automatically establish sufficient capacity across the wider transmission network. Since the project required future transmission system strengthening, its connectivity application was covered under Clause 7.3 of the Connectivity Procedure, 2025.
The commission reiterated that developers must follow approved regulatory procedures and individual exemptions cannot be granted against mandatory requirements. Accordingly, GERC dismissed the petition and directed Parighosh Realtors to furnish the ₹40 crore Bank Guarantee for securing final grid connectivity for its proposed 200 MW wind-solar hybrid project.