Sineng
NewsPolicy & RegulationsRajasthan High Court Rejects Retrospective 20% Local Content Rule For Renewable Energy...

Rajasthan High Court Rejects Retrospective 20% Local Content Rule For Renewable Energy Projects

The Rajasthan High Court has ruled that state power authorities cannot retrospectively impose a mandatory 20% domestic content requirement on renewable energy developers after contracts have been awarded. The judgment protects clean energy companies from additional procurement obligations introduced after the completion of competitive bidding processes.

Oriana

In a significant judgment delivered on November 18, 2026, Justice Anand Sharma allowed eleven connected writ petitions filed by renewable energy developers, including MIPHI Semicon India Private Limited and Ultravibrant Integrated Energy Limited, against the State of Rajasthan and Rajasthan Rajya Vidyut Utpadan Nigam Limited (RVUNL).

ReNew

The dispute arose from a global competitive tender issued by RVUNL in August 2025 for developing 500 MW/2,000 MWh of standalone Battery Energy Storage Systems (BESS) across Rajasthan. The project was supported by the central government’s Viability Gap Funding (VGF) scheme and was intended to improve the utilisation of surplus renewable electricity by storing excess solar and wind power for supply during peak demand periods.

Following the e-reverse auction, the petitioning companies emerged as successful bidders at a tariff of ₹2,85,000 per MW per month. RVUNL issued Letters of Award (LoAs) on December 19, 2025, which the successful bidders formally accepted by December 23, 2025.

The controversy began on December 24, 2025, when the Union Ministry of Power issued a directive requiring procuring agencies to ensure a minimum of 20% local content in total project costs. The requirement also covered indigenously developed Energy Management System software.

Based on this directive, RVUNL issued notices to the successful bidders in January 2026, asking them to provide undertakings confirming compliance with the domestic sourcing requirements within seven days. Subsequently, delays in submitting bank guarantees and executing formal agreements led RVUNL to issue show-cause notices in April 2026. The notices threatened cancellation of the awarded capacities and forfeiture of bid securities.

The developers challenged these actions before the Rajasthan High Court, arguing that the local content requirement had been introduced after the Letters of Award were issued and accepted. They maintained that the additional conditions could not be applied retrospectively to contracts already concluded.

Also Read  Solis Showcases C&I Energy Storage at REI Expo 2026, Marks 10 Years in India and Surpasses 10 GW in Shipments

The state government argued that the December 2025 directive only clarified existing Make in India procurement policies and General Financial Rules. It also highlighted the public interest involved in preventing the wastage of surplus renewable energy. The government further submitted that several developers had already provided the required undertakings.

Rejecting the state’s arguments, the High Court held that a concluded contract had been formed once the developers unconditionally accepted the Letters of Award. The court observed that the Ministry of Power’s directive included a transitional provision applicable only to pending tenders where contracts had not yet been awarded.

The court ruled that introducing additional technical and financial obligations after the bidding process violated Article 14 of the Constitution and established principles of contract law. It also clarified that undertakings submitted under administrative pressure could not make an otherwise unlawful requirement valid.

Accordingly, the High Court quashed RVUNL’s January 2026 local content directive and the April show-cause notices. However, developers have been directed to complete the remaining original contractual formalities, including submitting performance bank guarantees, within 15 days.


Discover more from SolarQuarter

Subscribe to get the latest posts sent to your email.

LEAVE A REPLY

This site uses Akismet to reduce spam. Learn how your comment data is processed.

RELATED ARTICLES

Subscribe Today

GET EXCLUSIVE FULL ACCESS TO PREMIUM CONTENT

SUPPORT CLEANTECH JOURNALISM

EXPERT ANALYSIS OF AND EMERGING TRENDS

TOPICAL VIDEO WEBINARS

Get unlimited access to our EXCLUSIVE Content and our archive of subscriber stories.

Exclusive content this week

Latest article

More articles

- Advertisement -Newspaper WordPress Theme