The Maharashtra Electricity Regulatory Commission (MERC) has approved tariffs for the Maharashtra State Electricity Distribution Company Limited (MSEDCL) to procure 2,000 MW/4,000 MWh of battery energy storage capacity for a period of 15 years. In its order dated November 23, 2026, in Case No. 218 of 2026, the commission approved a monthly tariff of Rs. 2,40,000 per MW for Part-A and Rs. 2,38,000 per MW for Part-B. The procurement will be supported through Viability Gap Funding (VGF) under the Power System Development Fund (PSDF).
The approved projects will operate on a one-cycle-per-day basis, with a two-hour discharge duration. The tender was divided into two parts under a Request for Selection issued on June 30, 2026. Part-A covers 500 MW/1,000 MWh of battery storage capacity at MSEDCL substations and is exclusively reserved for eligible developers under the Mukhyamantri Saur Krushi Vahini Yojana (MSKVY) 2.0. Part-B covers 1,500 MW/3,000 MWh across Maharashtra State Electricity Transmission Company Limited (MSETCL) substations and locations co-located with existing solar projects contracted with MSEDCL.
The tender received 45 bids, which were opened in August 2026. Reverse auctions conducted on August 31, 2026, determined the final tariffs after the highest bidders were disqualified in accordance with the tender conditions. MSEDCL subsequently issued Letters of Award (LoAs) to the selected developers on September 18, 2026.
In Part-A, five developers were selected, with Oriana Power Limited securing the largest allocation of 400 MW. In Part-B, seven developers received awards. Oriana Power Limited secured 500 MW, followed by BSL Engineering Service Limited with 300 MW and ArMee Infotech Limited with 250 MW. All selected developers have committed to maintaining a minimum round-trip efficiency of 85%.
The latest procurement process follows an earlier 2,000 MW/4,000 MWh battery storage tender for which MERC had approved a tariff of Rs. 1,65,998 per MW per month on March 6, 2026. However, the Appellate Tribunal for Electricity set aside that approval on June 5, 2026. The Supreme Court subsequently stayed the tribunal’s decision on September 9, 2026.
In an affidavit submitted on November 5, 2026, MSEDCL clarified that the new procurement exercise is separate from the ongoing legal proceedings. It also stated that approval of the new tender does not depend on the Supreme Court’s interim order. VGF support of up to Rs. 18 lakh per MWh has been reserved exclusively for developers selected under the new bidding process.
MERC observed that the procurement process was transparent and that the discovered tariffs were reasonable compared with recent battery storage tenders conducted by other utilities, considering the available VGF support.
The commission also permitted the approved storage capacity to count towards MSEDCL’s Energy Storage Obligation, as applicable regulatory targets increase to 4% by FY 2029-30. The projects are expected to be commissioned during FY 2027-28.
MERC has directed MSEDCL to execute Battery Energy Storage Purchase Agreements with all selected developers within 15 days of the order and submit copies of the signed agreements to the commission for its records.