The Solar Energy Corporation of India (SECI) has announced Extension of Timelines for Implementation of 97.5 kWp Grid Connected Roof Top Solar PV System Scheme for Government Buildings in different Zones of India under CAPEX and RESCO Model.
Based on the approval accorded by the Competent Authority, the lockdown due to COVID-19 has been treated as Force Majeure and it has been decided to grant suitable time extension, the notice stated.
The revised timelines for the Successful Bidder to complete the roofs identification and survey, submission of Project Sanction Documents, Design, Engineering, Manufacture, Supply, Storage, Civil Work, Erection, Testing & Commissioning is 20th January 2021 in case of Zone-1, Zone-2, Zone-3 and by 22th April 2021 in case of Zone-4.
The time for submission of project sanction documents is upto 20th October 2020 in case of Zone-1, Zone-2, Zone-3 and 20th January 2021 in case of Zone-4.
On 13th May, The Solar Energy Corporation of India (SECI) announced the list of successful bidders selected for its 97.5 MW rooftop solar tender. There are 52 winners in total.
In Zone 1, Part A, B, and C Rajasthan Electronics & Instruments Limited, Broil Solar Energy Private Limited And Pink city Energy Private Limited has been allotted the highest capacity of,1000,5000 AND1000 kwp individually.
In Zone 2, Part A most of the companies have been allotted capacity of 1000 Kwp, Part B AMP Solar has been allotted the highest capacity of 5000 Kwp and in Part C Solanki energy and Relitech Enercon Opc Pvt Ltd has been allotted the highest capacity of 250 Kwp.
In Zone 3, Part A most of the companies have been allotted capacity of 1000 Kwp, In Part B Sunsource energy Pvt Ltd. has been allotted the highest capacity of 4000 Kwp and three companies have been allotted 250 Kwp under Part C.