Solar Energy Corporation of India Limited (SECI) recently issued Public Notice of Amendment regarding the tender for Selection of Solar Power Developers to Set up a 10 MW Grid Connected Solar PV Power Project installed at Bagru, Jaipur District, Rajasthan under Competitive Bidding.
In June, The Solar Energy Corporation of India Limited (SECI) issued a notice inviting tender (NIT) for Selection of Solar Power Developers for Setting up of 10 MW Grid Connected Solar PV Power Project to be installed at Bagru, Jaipur District, Rajasthan under Global Competitive Bidding.
The new major amendments are as follows: SECI lowered the maximum tariff payable to the project developer from Rs. 3.20 /kWh to Rs.3.14 /kWh.SECI highlighted it would reject bids higher than INR 3.14 /kWh.
The project connection point is now at 33kV of the 33kV/220kV at Rajasthan State Industrial Development and Investment Corporation (RIICO) grid substation in Bagru.
The new amendment also states that transmission lines could be built through the National Highways Authority of India (NHAI) and RIICO Industrial area routes.
Recently, The Solar Energy Corporation of India Limited (SECI) issued a notice of extension for its 10 MW Grid Connected Solar PV Power Project which is to be installed at Bagru, Jaipur District, Rajasthan.
The last date of bid submission (both online and offline) is hereby extended from 24.07.2020 to 07.08.2020 (15:00 HRS). The opening date of the techno-commercial bid is extended till 07.08.2020.
To participate in this bid the Net Worth of the Bidder shall be equal to or greater than INR 90 Lakhs per MW of the quoted capacity, as on the last date of previous Financial Year, i.e. FY 2019-2020 or FY 2018-2019.