NTPC Reduces EPC Solar Tender Capacity From 600 to 500 MW; Limits Project Within Gujarat

NTPC has recently revised its previous tender of 600 MW solar projects for EPC package in the country. The tender capacity has now been reduced to 500 MW .

Growatt

The project location now is limited to Gujarat.

The last date for submitting bids was also revised from 22 June  2020 to to 24 November 2020.

In May, National Thermal Power Corporation Limited (NTPC) floated an Invitation For Bids (IFB) for EPC package with land for development of ISTS grid connected solar PV projects up to 600 MW.

The scope of work for this tender includes Design,  Engineering,  Manufacturing,  Supply,  Packing  and  Forwarding, Transportation,  Unloading,  Storage,  Installation  and  Commissioning  of  grid connected Solar PV projects located anywhere in India on turnkey basis.  

To know more refer to the document below:


Discover more from SolarQuarter

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.

RELATED ARTICLES

Subscribe Today

GET EXCLUSIVE FULL ACCESS TO PREMIUM CONTENT

SUPPORT CLEANTECH JOURNALISM

EXPERT ANALYSIS OF AND EMERGING TRENDS

TOPICAL VIDEO WEBINARS

Get unlimited access to our EXCLUSIVE Content and our archive of subscriber stories.

Exclusive content this week

UPCOMING EVENTS

Latest article

More articles

- Advertisement -Newspaper WordPress Theme