NTPC Ltd, India’s largest integrated energy company, has declared the COD of the last part capacity of 20 MW out of 100 MW Ramagundam Floating Solar PV Project.

pixon energy

Ramagundam Floating Solar PV Project is India’s largest Floating Solar Plant commissioned by NTPC.

With the successful commissioning, the last part capacity of 20 MW out of 100 MW Ramagundam Floating Solar PV Project at Ramagundam, Telangana is declared on Commercial Operation w.e.f. 00:00 Hrs. of 01.07.2022.

The total installed capacity of the company is 69,134.20 MW having 23 coal based, 7 gas based, 1 Hydro, 19 renewable energy projects. Under JV, NTPC has 9 coal based, 4 gas based, 8 hydro and 5 renewable energy projects.

Last month NTPC had announced the beginning of commercial operation of its 15 MW solar capacity at Kawas Solar Project in Gujarat.