The procedure outlines a step-by-step process for connecting generating stations, including renewable energy sources and captive power plants, to the intra-state transmission system in Tamil Nadu. This process ensures that new entities can be smoothly integrated into the existing network without disrupting its stability or reliability.
To begin the process, any entity that needs access to the transmission system must apply. This application must include a detailed project report that covers technical specifications, the expected load or generation capacity, and the proposed connection point to the transmission system. Once the application is submitted, the transmission utility reviews it to determine whether the existing network can support the new connection, taking into account current capacity and future expansion plans.
If the application is found to be feasible, the transmission utility issues a letter of intent to the applicant. This letter outlines the terms and conditions for granting connectivity, including technical requirements, the timeline for establishing the connection, and any additional costs. The applicant must then confirm their acceptance of these terms and make the necessary arrangements to proceed with the connection.
Coordination between the transmission utility, the applicant, and other stakeholders is crucial throughout this process. This coordination helps ensure that the new connection does not negatively affect the existing network. The applicant must also comply with all relevant technical standards and grid code regulations, as specified by the regulatory authority.
In some cases, the transmission system may need upgrades or modifications to accommodate the new connection. When this happens, the transmission utility is responsible for carrying out these upgrades. The costs for these upgrades are usually covered by the applicant, depending on what modifications are needed.
The procedure also includes guidelines for temporary connectivity. This type of connectivity might be necessary for testing purposes or short-term projects. Temporary connectivity is granted under specific conditions and is usually limited to a short period. The applicant must still meet the same technical standards and regulations as required for permanent connections.
The final stage of the process involves formally commissioning the new connection. This includes a series of tests and inspections to make sure that the infrastructure meets the required standards and can operate as needed. Once these tests are completed, the transmission utility gives its final approval, and the applicant is officially connected to the intra-state transmission system.
Overall, this detailed procedure ensures that new generating stations and other entities are integrated into the transmission network in an orderly and efficient manner. The process emphasizes the importance of meeting technical standards, coordinating with stakeholders, and completing all necessary steps promptly to establish a stable connection.