A new Wood Mackenzie study reveals that U.S. utilities are preparing for substantial growth in large load capacity, with 116 gigawatts (GW) already committed or under constructionโequivalent to 15.5% of the nationโs current peak electricity demand. When projects under advanced discussion or short-term forecasts are included, the total rises to 147 GW, or 20% of peak demand. The report, โNo Turning Back: An Analysis of Utility Large Load Pipelines,โ highlights that much of this capacity is expected to come online within this decade. By 2030, about 60 GWโrepresenting 8% of todayโs peak demandโis projected to be added.
Utilities anticipate 93 GW will be operational by 2035, although little information has been disclosed about projects beyond that year. Ben Hertz-Shargel, Wood Mackenzieโs global head of Grid Edge, noted that utilities are rapidly committing to new loads this decade, but warned that the market may struggle to meet this demand on the planned timeline, potentially delaying projects. The study also points to a shift in where large load projects are being developed. Currently, 91% of the 17 GW under construction is located in regulated markets.
However, 54% of committed capacity not yet under construction and 65% of advanced-discussion capacity are planned for deregulated markets. Nearly three-quarters of these high-confidence loads are concentrated in the ERCOT and PJM regions. According to Hertz-Shargel, the growing presence of projects in deregulated marketsโespecially in ERCOTโcarries risks such as supply shortfalls and price increases for smaller customers. These challenges have already prompted market interventions in Texas and PJM, with further regulatory actions expected.
The report warns that pipeline certainty is declining, as new requests outpace the advancement or withdrawal of existing projects. While some utilities have slightly increased their high-confidence capacity, its overall share of the pipeline has decreased in recent quarters. Data centers are a major factor adding to this uncertainty. For projects exceeding 300 MW, the ramp-up to full contract capacity can take much longer than four years, making it difficult to predict when the grid will actually experience the new load. Hertz-Shargel emphasized that the timing of demand ultimately depends on data center developers, not just utilities.
Discover more from SolarQuarter
Subscribe to get the latest posts sent to your email.