SOFAR
Sineng

Juniper Green Energy Expands Its Renewable Portfolio With Two Newly Commissioned Projects Of ~64 MWp In Gujarat And Maharashtra

0
422
Representational image. Credit: Canva

Juniper Green Energy Limited has successfully commissioned approximately 64 MWp of new renewable energy capacity across two major projects located in Gujarat and Maharashtra. This achievement includes the commissioning of a wind power project in Gujarat and the solar component of a hybrid power project in Maharashtra. The milestone reflects Juniper Green Energyโ€™s strong execution capabilities and its continued dedication to advancing Indiaโ€™s clean energy transition.

In Gujarat, the company commissioned around 28 MW of wind power capacity from its 70 MW wind power project situated in Devbhumi Dwarka. This project was executed through its subsidiary, Juniper Green Kite Private Limited, and achieved commissioning on October 15, 2025 โ€” nearly four months ahead of its Scheduled Commercial Operation Date (SCOD) of February 7, 2026. The Power Purchase Agreement (PPA) for the total 70 MW project was signed with Gujarat Urja Vikas Nigam Limited on February 8, 2024. The early completion of this project demonstrates Juniper Green Energyโ€™s efficiency in managing large-scale renewable developments and its ability to meet timelines ahead of expectations.

Also Read  Voltide Solutions Pvt. Ltd. and JEM Energy Launch Made-in-India BESS-as-a-Service Model for Commercial Backup Power in India

In Maharashtra, the company successfully commissioned the 36 MWp solar component of its 133 MWp hybrid power project in Nanded district through its subsidiary, Juniper Green Spark Ten Private Limited. This solar capacity was commissioned on October 12, 2025 โ€” an impressive 13 months ahead of schedule. The PPA for this project was executed with the Maharashtra State Electricity Distribution Company Limited on November 18, 2024, with an SCOD of November 17, 2026. The early commissioning highlights the companyโ€™s focus on accelerating renewable capacity addition to meet the nationโ€™s growing demand for sustainable energy.

Commenting on the achievement, Ankush Malik, CEO of Juniper Green Energy, said, โ€œThe dual commissioning across Gujarat and Maharashtra, completed months ahead of schedule, is a testament to our execution capabilities and commitment to speedy delivery. At Juniper Green Energy, we remain focused on driving Indiaโ€™s clean energy transition by consistently bringing reliable and sustainable power online sooner than expected.โ€

Also Read  JTEKT Corporation Powers Up 2,500 MWh Solar Carport In Kagawa Prefecture Through 20-Year PPA With Peak Energy

Through these successful project completions, Juniper Green Energy continues to reinforce its position as a leading renewable energy player in India. By consistently delivering projects ahead of schedule, the company demonstrates its commitment to operational excellence, sustainability, and contributing meaningfully to Indiaโ€™s ambitious clean energy goals.