The Rajasthan Electricity Regulatory Commission (RERC) has upheld the liability of Shri Om Agro Products to pay ₹15.86 lakh in relinquishment charges to the Rajasthan Rajya Vidyut Prasaran Nigam Limited (RVPN) following the premature surrender of long-term open access capacity. The Commission ruled that the subsequent conversion of captive wind power capacity into power sales to a distribution licensee does not exempt the generator from statutory surrender charges under the applicable regulations.
The petition was filed by Shri Om Agro Products against RVPN and other respondents, challenging the imposition of surrender charges and the disconnection of its wind power generators. The petitioner had established a 1.5 MW wind power plant in Jaisalmer, Rajasthan, of which 0.75 MW was allocated for captive consumption at its manufacturing facility in Jodhpur under an open access wheeling agreement signed in March 2013.
However, due to a substantial decline in business activity and commercial demand, electricity consumption at the petitioner’s factory gradually reduced and eventually reached zero. As a result, the company sought permission to convert its 0.75 MW captive capacity into a preferential tariff-based power sale arrangement with the state distribution licensee.
Following the necessary administrative approvals, an amended Power Purchase Agreement (PPA) was executed in July 2024, allowing the petitioner to transition the capacity from captive consumption to power sales.
Subsequently, RVPN issued demand notices seeking payment of transmission-related dues and surrender charges totalling ₹15,86,864 under Regulation 14 of the RERC Open Access Regulations, 2016. The petitioner challenged these charges, arguing that the transmission infrastructure continued to be utilised by the distribution licensee after the capacity transition. Therefore, according to the petitioner, no transmission capacity was stranded and no actual financial loss had been incurred by RVPN.
After the petitioner disputed the demand and failed to deposit the charges, RVPN ordered the disconnection of the wind power plant from the pooling station in May 2025.
RVPN argued that the petitioner had relinquished its long-term open access rights before completing the mandatory 12-year period. It maintained that such premature relinquishment attracted surrender charges under the regulations, irrespective of whether the capacity was subsequently allocated to a distribution licensee.
In its order, RERC observed that Regulation 14(2) provides a normative mechanism for calculating relinquishment charges at 66% of the applicable transmission charges for a maximum period of three years. The Commission clarified that the liability does not depend on proving actual stranded transmission capacity or financial losses.
Accordingly, RERC upheld RVPN’s demand and directed Shri Om Agro Products to clear the outstanding balance relinquishment charges. The Commission also upheld its interim directions concerning partial payment and reconnection of the wind power plant.