Sineng
NewsPolicy & RegulationsCERC Allows Amendment In Safeguard Duty Dispute Linked To Renewable Power Supply

CERC Allows Amendment In Safeguard Duty Dispute Linked To Renewable Power Supply

The Central Electricity Regulatory Commission (CERC) has permitted Chhattisgarh State Power Distribution Company Limited (CSPDCL) to amend its petition in an ₹85.28 crore safeguard duty dispute involving Adani Solar Energy Jaisalmer One Private Limited and other parties. In an order dated November 19, 2026, the commission ruled that the proposed amendment is clarificatory in nature and does not change the basic scope of the original case.

Oriana

The four-member bench, headed by Chairperson Jishnu Barua, allowed CSPDCL to correct the reference to a customs notification in its prayer. The commission observed that the relevant 2018 notification had already been discussed in the original petition and that the proposed change would not introduce a new claim or alter the amount being sought.

ReNew

The dispute relates to a renewable energy scheme launched by the Ministry of New and Renewable Energy (MNRE) in 2018 for developing 2,500 MW of interstate transmission system-connected wind-solar hybrid power projects. The Solar Energy Corporation of India (SECI) was appointed as the nodal agency for implementing the scheme.

Following the bidding process and e-reverse auction in late 2018, Adani Solar received letters of award in January 2019 for 450 MW of capacity. SECI subsequently signed power supply agreements with CSPDCL for 400 MW and the Haryana Power Purchase Centre for 50 MW in June 2019. Power purchase agreements between Adani Solar and SECI were executed in December 2019. The project achieved its commercial operation date on December 4, 2022.

In its original petition, CSPDCL sought a declaration that the abolition of safeguard duty on imported solar cells constituted a Change in Law event. The distribution company claimed that the development entitled it to compensation of ₹85,28,38,326.10, along with carrying costs. It requested a downward revision of the levelized tariff or direct financial compensation.

Also Read  GERC Approves Tariffs For 450 MW/900 MWh Battery Storage Projects In Gujarat

CSPDCL filed an amendment application in September 2025, explaining that its claim calculation was based on the 15 percent safeguard duty applicable when bids were submitted on November 20, 2018. This duty was imposed under Customs Notification No. 01/2018-Customs (SG), dated July 30, 2018. However, the original prayer had inadvertently referred only to Notification No. 02/2020-Customs (SG), dated July 29, 2020.

Adani Solar opposed the amendment, arguing that it was delayed and barred by the three-year limitation period. The company also maintained that solar module procurement began in October 2021, after both notifications had expired. Therefore, no safeguard duty was paid or saved, and the claim was based on assumptions rather than actual financial impact.

After examining the submissions and relevant legal provisions, including Order VI Rule 17 of the Code of Civil Procedure, CERC concluded that allowing the amendment would not prejudice Adani Solar or change the original claim amount.

The commission clarified that its order does not determine the merits of the underlying safeguard duty dispute. It directed the parties to complete their pleadings within four weeks.


Discover more from SolarQuarter

Subscribe to get the latest posts sent to your email.

LEAVE A REPLY

This site uses Akismet to reduce spam. Learn how your comment data is processed.

RELATED ARTICLES

Subscribe Today

GET EXCLUSIVE FULL ACCESS TO PREMIUM CONTENT

SUPPORT CLEANTECH JOURNALISM

EXPERT ANALYSIS OF AND EMERGING TRENDS

TOPICAL VIDEO WEBINARS

Get unlimited access to our EXCLUSIVE Content and our archive of subscriber stories.

Exclusive content this week

Latest article

More articles

- Advertisement -Newspaper WordPress Theme