NewsUPERC Orders SECI To Refund Performance Bank Guarantee To Solar Developers

UPERC Orders SECI To Refund Performance Bank Guarantee To Solar Developers

Uttar Pradesh Electricity Regulatory Commission (UPERC) identified the COVID-19 epidemic, delays in tariff approval, and issues with electricity procurement procedures as contributing factors in project delayed completion, thus, ordering Solar Energy Corporation of India (SECI) to refund the performance bank guarantee to ReNew Power’s subsidiaries.

Growatt

Because of delays in finishing 150 MW grid-connected floating solar power projects, SECI has called for the encashment of the performance bank guarantee (PBG). The developers had provided PBG of Rs. 1.13 million/MW.

Earlier, after winning an auction to build 150 MW of floating solar projects on Rihand Dam, ReNew Solar Power and Auxo Sunlight encountered delays because of lockdowns across the nation and supply chain concerns.

They asked SECI for an extension of the project’s financial closure and commissioning, which was approved.

However, the solar developers claimed that SECI had postponed submitting the petition for the approval of the tariff to the relevant body. As a result, the Commission rejected the developers’ request for a deadline extension.

In order to seek an extension, SECI then required the developers to sign an agreement waiving a number of contractual rights, which the developers later discovered to be against the power purchase agreement (PPA) and the COVID-19 relief recommendations of the Ministry of New and Renewable Energy (MNRE).

The developers, thereafter, asked SECI for an extension of the project schedules, but they were turned down. 

The agency informed the developers that they had not reached financial closure, leading to the encashment of the PPA. Therefore, in response, the developers petitioned the Allahabad High Court for an extension of the project deadlines as well as for the PBG to not be cashed in. 

Also Read  GERC Gives Final Opportunity To Developer In 40 MW Wind-Solar Hybrid Project Dispute In Gujarat

The court granted an interim injunction stopping the encashment of the PBG and directed the parties to approach the Uttar Pradesh regulator.

The Commission noted that SECI should return the PBG to the developers because the delay was the result of a force majeure incident and not the developers’ fault.

The Commission determined that factors such as COVID-19, the monsoons, delayed fulfillment of 100 MW of floaters, and other purchase orders, including delays in the signature of water and land leasing agreements, all contributed to the project’s implementation delay.

In addition, UPERC reasoned that the developer was not to blame for the delays in commissioning caused by the signing of the PPA and PSA, submitting a petition for tariff determination, or procuring electricity. Thus, the petitioners were ordered to be freed from the PPA and PSA.


Discover more from SolarQuarter

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.

RELATED ARTICLES

Subscribe Today

GET EXCLUSIVE FULL ACCESS TO PREMIUM CONTENT

SUPPORT CLEANTECH JOURNALISM

EXPERT ANALYSIS OF AND EMERGING TRENDS

TOPICAL VIDEO WEBINARS

Get unlimited access to our EXCLUSIVE Content and our archive of subscriber stories.

Exclusive content this week

UPCOMING EVENTS

Latest article

More articles

- Advertisement -Newspaper WordPress Theme