Iberdrola Australia Selected to Develop VNI West Transmission Project Linking Victoria and New South Wales

0
222
Representational image. Credit: Canva

Iberdrola Australia has been selected as a strategic partner to develop the VNI West (Victoriaโ€“New South Wales Interconnector West), a major transmission project that will connect the states of Victoria and New South Wales. The project marks a key step in Iberdrolaโ€™s strategy to invest in critical grid infrastructure in markets with strong and stable regulatory frameworks.

The 240 km, 500 kV double-circuit transmission line will increase bidirectional transfer capacity by up to 3.5 GW, unlocking new renewable generation across both states. VNI West will enhance grid reliability, support Victoriaโ€™s clean energy transition, and deliver long-term economic and social benefits to local communities.

In the first phase, Iberdrola will collaborate with VicGrid on engineering design, financial and technical planning, and environmental and regulatory approvals. The projectโ€™s completion is targeted for 2030, reinforcing Australiaโ€™s decarbonisation goals and energy security ambitions.


Discover more from SolarQuarter

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.