GoodWe- Reshaping Smart Energy

SECI Issues EPC Tender for 100 MW Floating Solar Project in Jharkhand

0
396

Reading Time: 2 minutes

Growatt

Solar Energy Corporation of India Limited (SECI) Issue Tender for supply of 100 MW (AC) Floating Solar PV Project having 10 years plant O&M at Getalsud Dam, Ranchi, Jharkhand, India.

SECI has applied for financing from the World Bank toward the cost of the Project of Innovation in Solar Power and Hybrid Technologies and intends to apply part of the proceeds toward payments under the Contract for the The Design, Engineering, Supply, Construction, Erection, Testing & Commissioning of 100 MW (AC) Floating Solar PV Project having 10 years plant O&M at Getalsud Dam, Ranchi, Jharkhand India under International competitive bidding.

SECI now invites online Bids from eligible Bidders for The Design, Engineering, Supply, Construction, Erection, Testing & Commissioning of 100 MW (AC) Floating Solar PV Project having 10 years plant O&M at Getalsud Dam, Ranchi, Jharkhand India under International competitive bidding.

Scope of work includes Design, Engineering, Supply, Construction, Erection, Testing & Commissioning of 100 MW (AC) Floating Solar PV Project having 10 years plant O&M at Getalsud Dam, Ranchi, Jharkhand.

Also Read  Tirupati Temple, NTPC to Sign MoU for Solar Projects

Tender submission final date is March 31, 2022 and the pre-bid meeting will take place on February 25, 2022.

All Bids must be accompanied by a Bid Security of the INR 7 Crores (Indian Rupees Seven Crores only) or USD 1 Mn (US Dollars One Million only) and the successful bidder shall deposit a performance security which shall be 10% of the contract value.

The minimum average turnover of a bidder should be Rs 263 crores or $35 million when calculated for the last three financial years. They should also have liquid assets and a line of credit of Rs 110 crores.

To participate developer should have installed ground mounted solar projects of at least 50 MW in the last five years. The developer should also have completed two projects of 10 MW each and should have been in operation for at least six months.

The work should be commence within 20 days from the signing of the agreement. The completion period for the whole of the plant facilities is 18 months till commissioning from the effective date. In case of delay liquidate damage would be 0.5% per week, subject to maximum of 5% of the EPC contract value.

Also Read  Kerala Electricity Board Invites Bids To Procure 150 MW Solar Power To Meet RPO

Tender Document:

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.