Sineng
UPEX 2026

Bombay High Court Examines MERC Order Dispute On Solar Tariffs And Natural Justice Principles

1
191
Representational image. Credit: Canva

The High Court of Judicature at Bombay delivered an important judgment on April 24, 2026, in a case involving solar power developers and state electricity regulators in Maharashtra. The dispute was brought by the Distributed Solar Power Association, along with AMPIN Energy Green Fifteen Pvt Ltd and Radiance MH Sunrise Nine Private Limited, against the Maharashtra Electricity Regulatory Commission.

The case revolves around an order issued by the commission on March 25, 2026, following a review of the Multi-Year Tariff framework for the period 2025 to 2030. The petitioners challenged this order, claiming it failed to follow directions given earlier by the High Court in its November 3, 2025, ruling.

According to the petitioners, the earlier ruling had sent the matter back to the commission with clear instructions to follow the principles of natural justice. This required the regulator to properly hear all stakeholders and consider their objections before making a final decision. However, the petitioners argued that although hearings were conducted, their concerns were not meaningfully addressed.

Also Read  First Ever Solar Contractors Meet Varanasi 2026 Marks a Strong Debut in the Region

They claimed the commissionโ€™s order lacked proper reasoning and did not explain why specific objectionsโ€”particularly those related to Time of Day tariffs and banking provisionsโ€”were rejected. The petitioners described the order as โ€œunreasonedโ€ and โ€œnon-speaking,โ€ suggesting it did not meet legal standards.

The petitioners also argued that the commission wrongly used its inherent powers to bypass established regulations, despite earlier restrictions imposed by the court. On this basis, they approached the High Court under Article 226 of the Constitution, seeking direct relief for what they described as violations of procedural fairness.

In response, the commission and the Maharashtra State Electricity Distribution Company Limited opposed the petition. They argued that the High Court should not hear the case because an alternative legal remedy is available. Under the Electricity Act 2003, aggrieved parties can appeal such decisions before the Appellate Tribunal for Electricity.

The respondents emphasized that the commission had conducted public hearings and reviewed submissions from more than 2,000 stakeholders before issuing its order. They also noted that the Supreme Court had earlier recognized the remand process and allowed parties to approach the appellate tribunal if they were dissatisfied with the outcome.

Also Read  CEA Proposes 2026 Draft Amendments To Accelerate Smart Meter Rollout Across India

While acknowledging its broad powers under Article 226, the High Court focused on whether it should exercise its discretion in this case. The key issue before the court is whether the alleged lack of detailed reasoning in the commissionโ€™s order amounts to a violation of natural justice significant enough to justify bypassing the established appellate process.


Discover more from SolarQuarter

Subscribe to get the latest posts sent to your email.

1 COMMENT

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.