waaree_jan
goodwemarch

Load Designing Can Aid Rooftop Solar Market Acceleration

0
438

“The world hates change yet it’s a fact it brings progress”. For any solar Rooftop project to be commercially viable ‘load designing’ is crucial. Distribution companies (DISCOMs) in India allow between 80% to 100% of sanctioned load as maximum Rooftop Solar PV (RSPV) capacity. A common practice followed to determine the capacity of a RSPV is the available roof area or the sanctioned load. Many a time it is observed that this conception mostly leads to systems being oversized that end up generating excess energy. It’s time to change the way we look at RSPV.

growatt_inside_jan

Figure1: Rooftop Solar PV at Jay Tea, Coimbatore

pixon_mar

Net-metering policy is now diminishing in most of the states. Ideally rooftop RSPV is best suited for industrial and commercial applications having sizeable daytime power requirements. The day solar radiation can best be captured into useful electricity for directly operating electrical loads. It is important to note that any Solar PV system cannot act as a substitute in meeting 24 X 7 energy demands unless it is stored. In other words they are supplementary in nature.

hoymiles
Also Read  NTPC Starts India’s First Green Hydrogen Blending Operation in PNG Network

It is a known fact that solar radiation varies with time hence it is essential to estimate the daily kWh a typical solar cell technology can produce instead of estimating the annual average. This gives a sense of the optimum capacity to be considered that will deliver energy that can be best utilised. Particularly where there are seasonal loads this exercise helps in optimising capacity.

powernsun

Case Study of Madhu Jayanti International Pvt. Ltd., Coimbatore

Madhu Jayanti International Pvt. Ltd. is an export unit processing tea bags based in Coimbatore. It has a south facing roof of 5,000 m2 that can best accommodate up to 500 kWp RSPV. The contract demand from the electric utility TANGEDCO is 1,250 kVA. The annual electricity consumption in 2018 was 7,56,744 kWp. With these coordinates the company received offers for RSPV ranging from 500 kWp – 750 kWp. 

While designing the capacity net-metering option was not considered instead suggested in captive mode. The Electricity Act in India permits prosumers to set up captive power plants if they consume 51% or more power. 

Also Read  Supply Security Through Hydropower Should Enable Laos To Expedite Renewables Development, Says Report

Figure 2 below shows the flow chart of exercise carried.

Figure 2: Flow chart to optimise Solar PV capacity for sunny time demand

A careful assessment of the loads operating during sunny time on hourly basis and monthly basis was obtained as shown in Table 1

LoadsConsumption period (month name)
0900- 10001000-11001100-12001200-13001300-14001400-15001500-1600

Table 1: Sunny time daily load analysis

Next the daily solar radiation data was obtained and the optimum PV capacity was assessed by averaging the daily capacities as shown in Table 2. Excess energy during summer days being undesired hence the capacity was further optimised. 

MonthAvg. daily Power consumption kWhDaily  radiation (kWh/m2)Daily radiation post 10% correction factor for dust, temperature coefficient  & efficiency losses (kWh/m2)PV array capacity kWpDaily output (kWh) kWhSurplus/Deficit kWh

Table 2: Month-wise energy generation from solar PV and estimation of Surplus/Deficit

As per the exercise carried in Figure 2, the final capacity arrived was 300 kWp as against 500 kWp obtained from PV developers. This capacity was able to meet  99.7% of the sunny time loads for most of the days that operate continuously excluding the rainy days. The balance energy requirement during a non-sunny time period is obtained from TANGEDCO supply. 

Also Read  Solar and Wind Account for 92% of India's Electricity Capacity Additions in 2022, Says Ember Analysis

With this load the excess generation was avoided in absence of net metering policy and the payback period was little under 4 years.

BeneficiaryMadhu Jayanti International Pvt. Ltd.
LocationCoimbatore 11.02° N, 76.96° E
South facing shadow-free roof area (m2)5,000 
Month average solar radiation (kWh/m2/d)ay3.95 – 5.70 
Annual electricity consumption (kWh)7,56,744
Original Capacity suggested (kWp)500
Sunny time electricity consumption3,96,000
Final Solar PV Capacity (kWp)300
Savings obtained in %40%
Type of Solar PV cell technologyMono-PERC
Payback period against the original capacityLittle under 2 years

Load modelling is essential in order to benefit any beneficiary. Industrial and commercial consumers paying higher grid drawn electricity tariff can best benefit from RSPV even in absence of net metering. It also helps electric utilities in demand management. This can result certainly in rooftop solar market acceleration.

By: Jaideep N. Malaviya, Managing Director, Malaviya Solar Energy Consultancy

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.