During the operation and maintenance of a solar PV plant, we often power off and power on the inverter, which is normally related to the safety of equipment and the personal safety of O&M personnel but is there anything specific we should look out for during what is seemingly a very simple process? In this Solis Seminar, we will share some relevant tips for you.

1. Powering Off the Inverter

When powering off the inverter for maintenance,ย please follow the steps below:

โ‘ First, select the “Grid off” option through the inverter LCD. 

Main Menuโ†’Advanced Settingsโ†’Password 0010โ†’Grid ON/OFFโ†’ Grid OFF๏ผ›

โ‘กThen turn off the AC side breaker corresponding to the inverter and the nextย turn off the inverter DC switch. The reason for doing it in this order is: by opening the AC circuit breaker first, the PV system in an open circuit state, to make sure the DC switch is switch off under no current & load condition, which is good for DC switch lifetime and system safe.

Also Read  Sunkind India Secures 1 GW TOPCon G12R DCR Solar Cell Supply Through FY28 Ahead of ALMM List-II Rollout

It should be noted that even if the DC switch and AC breaker are turned off, the inverter will still be holding electricity. You should wait for 5~10 minutes and after checking that there is no electricity for both DC and AC, andย then safely disassemble the inverterย or check the PV plant. (Note: When removing and checking PV strings, please pay attention to measuring its voltage. You must ensure that the voltage of PV Strings is lower than 30V or unplug the PV strings of the inverter in the evening.๏ผ‰

2. Inverter Power-on and Grid-Connected Operation  

After maintenance of the PV plant or the inverter is completed, it is recommended to follow the steps below for power-on and grid-connected operation:

โ‘ ย After check all PV strings (positive and negative poles are not reversely connected) and the AC cable wiring is correctly installed (The line wire, neutral wireย and PE wireย are connected correctlyย ), first close the AC circuit breaker, and then close the inverter DC switch, which canย avoidย the 1 to 3 minutes of grid connection delay caused by the “NO GRID” alarm.ย 

Also Read  European Bank For Reconstruction And Development Highlights Bulgariaโ€™s Plan To Source Nearly Half Its Electricity From Renewables By 2030 In New Green Future Video

โ‘ก Then, select the “Grid on” option through the inverter LCD. 

Main Menuโ†’Advanced Settingsโ†’Password 0010โ†’Grid ON/OFFโ†’ Grid ON๏ผ›

โ‘ขYou must ensure that the grid parameters of the inverter are set to the local distributorโ€™s requirements. 

Please pay attention to all the DC data and AC parameters displayed on the LCD should are normally displayed before you leave the site.  

3. Conclusion

Although these are small points of attention and are easily overlooked, taking note of these finer details can lead to the components of your inverter working better and for longer, and at the same time improve the grid-tied efficiency of the overall PV system. 

If you have any other questions, you can contact Solis support engineers or go to http://www.solisinverters.com/aftersales.html