Sineng
UPEX 2026

MERC Dismisses ₹47.75 Crore Solar GST Compensation Claim Over Delay In Change In Law Notice In Maharashtra

1
125
Representational image. Credit: Canva

The Maharashtra Electricity Regulatory Commission (MERC) has dismissed a petition filed by Avaada MH Sustainable Private Limited (AMHSPL), which had sought compensation for increased project costs due to changes in Goods and Services Tax (GST) rates. The company had requested around ₹47.75 crore, citing additional expenses and carrying costs arising from GST notifications issued in late 2021.

The dispute relates to GST notifications dated September 30, 2021, and October 14, 2021, which increased the tax on solar power generating systems from 5% to effective rates of 12% and 13.8%. AMHSPL argued that this increase qualified as a “Change in Law” under its Power Purchase Agreement (PPA) with Maharashtra State Electricity Distribution Company Limited (MSEDCL). Based on this claim, the company sought compensation for the additional financial burden it said it had incurred. According to AMHSPL, the GST hike led to an extra cost of ₹33.83 crore under its Module Supply Agreement and ₹13.92 crore under its Engineering, Procurement, and Construction (EPC) contract.

Also Read  CleanMax, STT GDC Sign 21 MWp Solar PPA for Chennai Data Centres

However, a key issue in the case was the timing of the “Change in Law” notice submitted by the petitioner. As per Article 9.3.1 of the PPA, any affected party must issue a notice within seven days of becoming aware, or when it should reasonably have become aware, of such an event. While the GST changes came into effect in late 2021, AMHSPL submitted its first formal notice only on September 16, 2022, almost a year later.

AMHSPL defended this delay by stating that it became fully aware of the financial impact only after receiving clarified invoices from its contractors in September 2022. The company argued that it issued the notice within the required seven-day period from the date of this clarification. In response, MSEDCL maintained that GST changes are statutory in nature and publicly available, and therefore, the company should have been aware of them at the time they were notified. It also pointed out that AMHSPL’s suppliers were related entities, suggesting that the petitioner had access to relevant information much earlier.

Also Read  Northern Solar Records Strongest Quarter on EPCC Growth and Solar ATAP Momentum

After reviewing the arguments and evidence, the Commission sided with MSEDCL. It was observed that the seven-day notice requirement under the PPA is a mandatory condition that must be strictly followed. The Commission noted that AMHSPL had been receiving invoices reflecting the revised GST rates as early as October 2021, indicating that the company was aware, or should have been aware, of the changes at that time.

Based on these findings, MERC concluded that AMHSPL failed to comply with the contractual requirement of timely notification. As a result, the Commission ruled that the company was not eligible for compensation and dismissed the petition.


Discover more from SolarQuarter

Subscribe to get the latest posts sent to your email.

1 COMMENT

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.