In a recent announcement, the Union Minister for Power and New & Renewable Energy underscored the crucial need for 24×7 power availability to fuel India’s economic growth. While renewable energy sources play a pivotal role, the intermittent nature of solar and wind power poses challenges for consistent energy supply. The minister emphasized that until cost-effective energy storage solutions are widely available, the country will continue to rely on coal-based generation to meet its energy demands.

Growatt

The power landscape in India has witnessed a significant surge in demand, fueled by a growing economy and the addition of 2.86 crore new consumers. The peak demand, which stood at 1,35,000 MW in FY 2013-14, has skyrocketed to 2,43,000 MW in the current fiscal year (until Nov. 2023). Projections from the 20th Electric Power Survey anticipate a peak demand of 2,77,200 MW in FY 2026-27 and a staggering 3,66,400 MW in FY 2031-32.

According to the National Electricity Plan, India aims to achieve an installed capacity of 9,00,422 MW by 2031-32. This includes 2,84,467 MW of fossil-based capacity (comprising coal, lignite, and gas) and 6,15,955 MW of non-fossil-based capacity (including nuclear, large hydro, solar, wind, small hydro, biomass, and pumped storage projects), along with a substantial Battery Energy Storage System capacity of 47,244 MW / 236,220 MWh.

Also Read  JinkoSolar Showcase Cutting-Edge Solar Solutions at Power Uzbekistan 2026, Secures 1GW Framework Agreements with Four Distributors On-Site

To meet the projected coal/lignite-based capacity requirement of 2,83,000 MW by FY 2032, the government has planned an additional 80,000 MW. Currently, 27,180 MW is under construction, 31,010 MW is in advanced planning/development stages, and 29,720 MW is identified for future development.

In a bid to optimize existing resources, the Central Electricity Authority (CEA) has recommended the Renovation & Modernization and Life Extension of 148 coal-based power plant units, with a total capacity of 38,150 MW. CEA’s advisory to Thermal Power Utilities urges them not to retire or repurpose coal-based power stations before 2030, ensuring their availability post R&M activities.

The total installed Thermal Capacity, encompassing coal, lignite, gas, and diesel, currently stands at 2,39,072 MW, with notable contributions from states like Odisha and Maharashtra.

To cater to the burgeoning energy demand, the anticipated capacity additions by 2031-32 include 87,910 MW of Thermal Capacity, 42,014 MW of Hydro Capacity, 12,200 MW of Nuclear Capacity, and a staggering 375,279 MW of Renewable Energy Capacity, which comprises solar, wind, and other sources.

Also Read  KEC International Wins Rs. 2,518 Crore Orders, Securing 400/132/66 kV Transmission Lines in T&D Segment

In summary, with 132,148.5 MW of capacity currently under construction, India envisions a substantial addition of 517,403 MW by 2031-32. This ambitious expansion plan reflects the nation’s commitment to ensuring a robust and uninterrupted power supply, vital for sustaining its rapid economic growth and meeting the evolving energy needs of its citizens. As the country navigates this energy transition, balancing conventional and renewable sources remains a strategic imperative.