Juniper Green Energy Limited has commissioned an additional 6.25 MW of wind power capacity through its wholly owned subsidiary, Juniper Green Stellar Private Limited.
The newly commissioned capacity forms part of the company’s 200 MW Firm and Dispatchable Renewable Energy Project, according to a regulatory filing submitted to the NSE and BSE on September 8, 2026, under Regulation 30 of the SEBI LODR Regulations.
With this addition, the project has achieved 353.45 MWp of commissioned solar and wind capacity, along with approximately 201 MWh of battery energy storage capacity, against the project’s planned total capacity of 550.6 MWp and around 201 MWh of BESS.
Following the latest commissioning, Juniper Green Energy and its subsidiaries have reached approximately 2,594 MWp of operational renewable energy capacity and 500 MWh of BESS.