The Central Electricity Regulatory Commission (CERC) has recently issued an order addressing petitions filed by SolarOne Energy Private Limited concerning the timelines for achieving financial closure and scheduled commissioning of its 300 MW Gadag and Koppal power projects. The core issue revolved around the interpretation of previous CERC orders and the extent to which the Commission could modify or extend deadlines set in those orders, particularly in light of subsequent appellate decisions.
SolarOne Energy had sought an extension of time, arguing that certain directives from the CERC, specifically those outlined in an order dated April 21, 2024, imposed unrealistic timelines. The company contended that it had faced delays due to factors beyond its control and that the Commission had previously indicated it would consider further requests for time extensions. The company cited the complexities of project development and the Central Government’s guidelines, which typically allow 24 months for project commissioning, as justification for its request.
The Central Transmission Utility of India Limited (CTUIL), the respondent, opposed SolarOne’s petitions, arguing that the matters had already been adjudicated and that the CERC no longer had jurisdiction to modify its previous orders. CTUIL invoked the doctrine of merger, stating that the Appellate Tribunal for Electricity (APTEL) order had effectively merged the CERC’s earlier decisions, thereby precluding further modifications. Furthermore, CTUIL argued that SolarOne’s petition was essentially a delayed review request, filed well beyond the permissible timeframe.
The CERC, in its deliberation, examined the sequence of events and the various orders issued. The Commission had initially granted SolarOne certain relaxations, including restoring revoked connectivity and allowing a shift from the LOA/PPA route to a Land/Land Bank Guarantee (BG) route. However, these relaxations were contingent on meeting specific deadlines for financial closure and project commissioning.
The Commission noted that SolarOne had repeatedly sought extensions and clarifications, indicating a pattern of sequential requests rather than a concerted effort to meet the original deadlines. The CERC emphasized that connectivity is a scarce resource and that timely project execution is crucial to prevent the blocking of such resources.
In its final decision, the CERC ruled that SolarOne’s petitions were not maintainable. The Commission concluded that the liberty granted in previous orders to approach the Commission for further relief was intended to facilitate genuine progress, not to justify delays. The CERC directed CTUIL to proceed with the directions outlined in the April 21, 2024, order, effectively rejecting SolarOne’s request for additional time.
This decision underscores the CERC’s commitment to enforcing regulatory timelines and ensuring the efficient use of connectivity resources. It highlights the importance of adhering to prescribed schedules and the limitations on subsequent modifications to orders, especially after appellate decisions. The ruling is expected to have significant implications for project developers and the regulatory framework governing the electricity sector.
Discover more from SolarQuarter
Subscribe to get the latest posts sent to your email.






